Jasmine
Jasmine

The Jasmine field lies approximately 6 miles west of the Judy production facility in blocks 30/6a and 30/7a of the UK sector of the North Sea. The field was discovered in June 2006 by well 30/6-6 and its sidetrack 30/6-6z. Further exploration and appraisal has since taken place with the field consisting of a core development area plus potential upside. Production first began in 2013 following the installation of the Jasmine topsides within the J-Area. It comprises a Jasmine Wellhead platform (JWHP) and the Jasmine Living Quarters platform (JLQ) bridge-linked to the JWHP. Hydrocarbons are produced via a multiphase pipeline from the JWHP to the Judy Riser Platform for processing.
Block | 30/6a and 30/7a | ![]() |
Sector | U.K. Central North Sea | |
Approx Distance to Land | 130 nautical miles SE of Aberdeen | |
Water Depth | 80 metres (263 ft) | |
Hydrocarbons Produced | Gas & oil/liquids | |
Export Method | Via Judy Platform: From Judy, gas goes to Teesside via the CATS pipeline. From Judy, liquids go to Teesside via the Norpipe system. |
|
Manned/Unmanned | Manned | |
Operated/Non-Operated | Operated | |
% of Chrysaor Equity | 67.00% | |
First Production | November 2013 | |
Accommodation on Board | 38 | |
Key Commercial Terms | Currently there are no agreements in place with third parties for the transportation and/or processing of product via Jasmine. |
INFRASTRUCTURE INFORMATION
Entry Specification: |
The entry specification for any future third party production is dependent upon the point at which such production would enter the Jasmine facilities and the composition of production already being processed at that time. The entry specification will cover areas that affect onward processing and transportation as well as those which impact the Jasmine and Judy facilities e.g. slugging limitations and contaminants. |
Exit Specification: |
For liquid and gas exit specifications ex processing on Judy see Judy ICOP information. |
HIGH LEVEL CAPACITY INFORMATION
The basic capacity information is portrayed by colour coded 'traffic lights' that reflect thresholds of availability over the next 5 years
Available Capacities




Jasmine platform firm processing capacity available | Ullage as % of system capacity | Comment | |||||
---|---|---|---|---|---|---|---|
2021 | 2022 | 2023 | 2024 | 2025 | |||
Jasmine HP Separator processing capacity (GAS) | ![]() |
![]() |
![]() |
![]() |
![]() |
At 30 bar. Jasmine HP Separator is located on Judy. Capacity was reduced when separator pressure reduced to 20 bar in Q3 2019. | |
Jasmine HP Separator processing capacity (LIQUIDS) | ![]() |
![]() |
![]() |
![]() |
![]() |
At 30 bar. Jasmine HP Separator is located on Judy. Capacity was reduced when separator pressure reduced to 20 bar in Q3 2019. | |
Booster compressor capacity | Refer to Judy for treatment capacity as all Jasmine fluids are treated on Judy platform. | ||||||
Gas export capacity | Refer to Judy for treatment capacity as all Jasmine fluids are treated on Judy platform. | ||||||
Gas lift capacity | Refer to Judy for treatment capacity as all Jasmine fluids are treated on Judy platform. | ||||||
Produced water handling capacity | Refer to Judy for treatment capacity as all Jasmine fluids are treated on Judy platform. | ||||||
Dehydration capacity | Refer to Judy for treatment capacity as all Jasmine fluids are treated on Judy platform. | ||||||
H2S removal capacity | Refer to Judy for treatment capacity as all Jasmine fluids are treated on Judy platform. | ||||||
Water injection capacity | Refer to Judy for treatment capacity as all Jasmine fluids are treated on Judy platform. | ||||||
Last update: December 2020 .pdf copy available here |
Contact Information
Gillian O'Hara
T: 44 (0) 1224 205131
E:gillian.ohara@chrysaor.com